R.J. Grondin & Sons teamed up with Great Falls Construction in developing the last lot in the Gorham Industrial Park. The Grondin team is responsible for grubbing the 4-acre site, installation of erosion control measures while working along an adjacent wetland, installation of underground utilities. In addition, Grondin constructed a preload surcharge for the building footprint consisting of 20,000cy of material that will sit for 18 months on top of a wick-drain system. Once settlement has been completed, the surcharge will be used for fills and gravels for the site where a 21,000 sq ft multi-use commercial building will be constructed.